How the math works
Area: 20 ft × 12 ft = 240 sq ftThickness in feet: 4" ÷ 12 = 0.333 ftVolume: 240 × 0.333 = 80.00 cu ftAdd 10% waste: 80.00 × 1.10 = 88.00 cu ftCubic yards: 88.00 ÷ 27 = 3.26 yd³ → order 3.50 yd³80 lb bags: 88.00 ÷ 0.60 = 147 bags (60 lb: ÷ 0.45 = 196)Rebar: 8 bars × 19' 6" + 14 bars × 11' 6" = 317 LF → 17 sticks
Bag yields: 80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft, 40 lb ≈ 0.30 cu ft (Quikrete / Sakrete). 1 yd³ = 45 × 80 lb bags.
Trade pro tips
- 3.50 yd³ is under most plants' 4-yard minimum — ask about the short-load fee before ordering ready-mix.
- Order 5–10% extra. Subgrade is never perfectly flat, and running short mid-pour leaves a cold joint.
- Compact 4" of gravel base and slope the forms ¼" per foot away from any structure.
- Chair the rebar so it sits in the middle third of the slab — rebar lying on the dirt does nothing.
- Cut control joints ¼ of the slab depth, no more than 2–3 × the thickness (in feet) apart, within 6–18 hours.
Frequently asked questions
How many yards of concrete do I need for a 12x20 slab?
With 10% waste: 4" thick = 3.26 yd³ (order 3.50), 5" = 4.07 yd³ (order 4.25), 6" = 4.89 yd³ (order 5.00). A 12x20 slab is 240 sq ft.
How many 80 lb bags of concrete for a 12x20 slab 4 inches thick?
147 bags of 80 lb concrete (0.60 cu ft each) or 196 bags of 60 lb, including 10% waste. That is about 11,760 lbs of bags to haul.
How much rebar do I need for a 12x20 slab?
A grid at 18" on center both ways uses 8 bars running 20 ft and 14 bars running 12 ft — about 317 linear feet, or 17 twenty-foot sticks of #3 or #4 rebar, 112 ties and ~28 chairs.
How much does a 12x20 concrete slab cost?
Material only at 4": about $578 in ready-mix or $956 in 80 lb bags; at 6": about $825 ready-mix. Installed, 12x20 slabs typically run $6–$12 per sq ft ($1,440–$2,880) depending on region, access and finish.