How the math works
Area: 12 ft × 12 ft = 144 sq ftThickness in feet: 4" ÷ 12 = 0.333 ftVolume: 144 × 0.333 = 48.00 cu ftAdd 10% waste: 48.00 × 1.10 = 52.80 cu ftCubic yards: 52.80 ÷ 27 = 1.96 yd³ → order 2.00 yd³80 lb bags: 52.80 ÷ 0.60 = 88 bags (60 lb: ÷ 0.45 = 118)Rebar: 8 bars × 11' 6" + 8 bars × 11' 6" = 184 LF → 10 sticks
Bag yields: 80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft, 40 lb ≈ 0.30 cu ft (Quikrete / Sakrete). 1 yd³ = 45 × 80 lb bags.
Trade pro tips
- 2.00 yd³ is under most plants' 4-yard minimum — ask about the short-load fee before ordering ready-mix.
- Order 5–10% extra. Subgrade is never perfectly flat, and running short mid-pour leaves a cold joint.
- Compact 4" of gravel base and slope the forms ¼" per foot away from any structure.
- Chair the rebar so it sits in the middle third of the slab — rebar lying on the dirt does nothing.
- Cut control joints ¼ of the slab depth, no more than 2–3 × the thickness (in feet) apart, within 6–18 hours.
Frequently asked questions
How many yards of concrete do I need for a 12x12 slab?
With 10% waste: 4" thick = 1.96 yd³ (order 2.00), 5" = 2.44 yd³ (order 2.50), 6" = 2.93 yd³ (order 3.00). A 12x12 slab is 144 sq ft.
How many 80 lb bags of concrete for a 12x12 slab 4 inches thick?
88 bags of 80 lb concrete (0.60 cu ft each) or 118 bags of 60 lb, including 10% waste. That is about 7,040 lbs of bags to haul.
How much rebar do I need for a 12x12 slab?
A grid at 18" on center both ways uses 8 bars running 12 ft and 8 bars running 12 ft — about 184 linear feet, or 10 twenty-foot sticks of #3 or #4 rebar, 64 ties and ~16 chairs.
How much does a 12x12 concrete slab cost?
Material only at 4": about $330 in ready-mix or $572 in 80 lb bags; at 6": about $495 ready-mix. Installed, 12x12 slabs typically run $6–$12 per sq ft ($864–$1,728) depending on region, access and finish.