How the math works
Area: 20 ft × 20 ft = 400 sq ftVolume @ 4": 400 × (4 ÷ 12) = 133.33 cu ftAdd 10%: 133.33 × 1.10 = 146.67 cu ftCubic yards: 146.67 ÷ 27 = 5.43 yd³Tons: 5.43 × 1.4 = 7.60 tonsTruck loads: 19.01 tons ÷ 15 tons per tandem = 2
Trade pro tips
- At 4" deep, 20x20 takes 7.60 tons — a single dump truck delivery covers it.
- Build in layers: 4" of #3 (2"–3") stone, 4" of #57, then 2" of crusher run / dense grade on top.
- Lay non-woven geotextile over clay soil first — it stops stone from sinking.
- Crown the driveway ½" per foot so water sheds to the sides.
- Spread with a box blade and compact each layer before the next.
Frequently asked questions
How many tons of gravel do I need for a 20x20 driveway?
At 4" deep: 7.60 tons. At 6": 11.41 tons. A complete 3-layer driveway (4" #3 + 4" #57 + 2" crusher run) is 19.01 tons. All include 10% extra.
How many cubic yards of gravel for 20x20?
2": 2.72 yd³; 4": 5.43 yd³; 6": 8.15 yd³; 8": 10.86 yd³. 20x20 is 400 sq ft.
How many truck loads of gravel for a 20x20 driveway?
A tandem dump truck carries about 15 tons. 20x20 at 4" (7.60 t) is 1 load; the full 3-layer build (19.01 t) is 2 loads.
How much does a 20x20 gravel driveway cost?
Stone alone at 4" is about $303 (~$55/yd³). A 3-layer build runs roughly $747 in material plus 49 sq yd of fabric; delivery and grading are extra.